Schedule/Info
Phase 1
Oracle
Oracle
Phase 2
Stone/Park
Stone/Park
Phase 5&6
Campbell/Country Club
Campbell/Country Club
Phase 3&4
Alvernon/Swan
Alvernon/Swan
- Substantially complete
- Construction cost estimate $11 million
- Complete construction cost $7 million
- Utilities Clearance: Estimated Completion in December 2016
- Construction Period: 2017-2018
- Construction Contract Amount, Estimated: $14.5 Million
- Utilities Clearance: Approx. 12 months
- Construction Period: 2021-2025
- Estimated Construction Cost: $42 Million
- Phases 3 & 4 to be Built Concurrently
- Utilities Clearance: Approx. 12 months
- Construction to Start: 2026
- Estimated Construction Cost: $50 million
- Phases 5 & 6 to be Built Concurrently