Grant Road Improvement Project

Schedule/Info

Phase 1
Oracle
Phase 2
Stone/Park
Phase 5&6
Campbell/Country Club
Phase 3&4
Alvernon/Swan
  • Substantially complete
  • Construction cost estimate $11 million
  • Complete construction cost $7 million
more ›
  • Utilities Clearance: Estimated Completion in December 2016
  • Construction Period: 2017-2018
  • Construction Contract Amount, Estimated: $14.5 Million
more ›
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2021-2025
  • Estimated Construction Cost: $42 Million
  • Phases 3 & 4 to be Built Concurrently
more ›
  • Utilities Clearance: Approx. 12 months
  • Construction to Start: 2026
  • Estimated Construction Cost: $50 million
  • Phases 5 & 6 to be Built Concurrently
more ›