Grant Road Improvement Project

Schedule/Info

Phase 1
Oracle
Phase 2
Stone/Park
Phase 5&6
Campbell/Country Club
Phase 3&4
Alvernon/Swan
  • Substantially Complete
more ›
  • RTA Funding Period 2
  • Utilities Clearance: Estimated completion in December 2016
  • Construction Period: 2017-2018
  • Estimated Construction Cost: $17 million
more ›
  • RTA Funding Period 3 ( 2017-2021)
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2018-2020
  • Estimated Construction Cost: $28 Million
  • Phases 3 & 4 to be built concurrently
more ›
  • RTA Funding Period 3/4 (2021-2026)
  • Utilities Clearance: Approx. 12 months
  • Construction Period: 2021-2023
  • Estimated Construction Cost: $33 Million
  • Phases 5 & 6 to be built concurrently
more ›